Labour Requirement for Next Concrete Pour

1 reply [Last post]
zahid shaikh
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 24 Aug 2016
Posts: 35

My new Construction manager keeps asking me, in Next Week or Next Month we have planned These many Corewalls & Slab concrete casting. How much Carpenter,Steel fitter,etc. has been loaded in the programme for these slabs so I can plan the Manpower requirement for that work. He was probably getting this type of info in his previous company I guess.

I have been manually going into that activity and writing our the resource labour requiement by hand. Is there a way to Filter out the Resource by Resource name, if Not weekly atleast monthly labour requirement for the planned slab casting

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 22 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

create seperate resources they type of labor and the type of material being tracked

assign both of there to each activity

assign the proper units for labor it will be manhours

for material it wil be based whatever the material is being installed CY of concrete, tons of steel etc

if you do this for all of your activities you can select view resource usage profile and see how the units are forecated to be spend as the relate to time.