convert P6 file to MSP file

3 replies [Last post]
kamesh avasarala
User offline. Last seen 5 years 13 weeks ago. Offline

hi,

when we export P6 file to MSP file it is not converting all data into MSP rightly , like Lag is not getting in MSP, Actual finish dates are not getting correct and % column also nopt getting right in MSP converted file from P6 can you explain the procedure of export in more details 

Replies

Zoltan Palffy
User offline. Last seen 11 weeks 5 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

have you tired exporting it to an xml file  ?

David Kelly
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630

The issue is that it does not work. For example MSP and P6 calculate lags differently. To do the job properly you need to buy software to do the conversion. Collabro's Legare for example.

David Kelly
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630

The issue is that it does not work. For example MSP and P6 calculate lags differently. To do the job properly you need to buy software to do the conversion. Collabro's Legare for example.