Problem converting XER file from P6 v6.0 to P6 v17.2

1 reply [Last post]
Raul Santos
User offline. Last seen 6 years 41 weeks ago. Offline
Joined: 29 Oct 2009
Posts: 44
Groups: None

I'm getting an error message when trying to convert an XER file from an old version of P6 (version 6.0) to one of the latest versions of P6 (version 17.2).  I get the following error message: 

"An application vent has been intercepted. Please note the event code for reference.

Event code: AVAA0-0863-B"

Anyone knows how to solve this problem?

Replies

Zoltan Palffy
User offline. Last seen 5 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

you do not need to convert it just import it ALL software is downwardly compatible.