Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

WBS disappeared from the programme

4 replies [Last post]
M Sagar
User offline. Last seen 9 years 28 weeks ago. Offline
Joined: 9 Jan 2015
Posts: 6
Groups: None

Hi guys,

I am facing a weird problem with WBS on a specific programme. When I am grouping the activities by WBS under the Group & Sort option its not getting grouped so. Plus, under the WBS view its noy showing any dates and activities against each WBS. Actually, there are many activities under each WBS and there are various level of those WBSs as well. Please help!

Thanks!

Normal programme's WBS view

3659
capture_normal_wbs.png

The problematic programme's WBS view

3658
capture1.png

Replies

Zoltan Palffy
User offline. Last seen 16 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

if you have an older version of the schedule you can export the activity and wbs assignment to excel. Then change the first part of the wbs to match the project id in excel save it then import it into your schedule where the assignments are missing. 

Zoltan Palffy
User offline. Last seen 16 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

if you have an older version of the scheduel you can export the activity and wbs asssignment to excel. Then change the first part of the wbs to match the project id in excel save it then import it inot your schedule where the assignments are missing. 

M Sagar
User offline. Last seen 9 years 28 weeks ago. Offline
Joined: 9 Jan 2015
Posts: 6
Groups: None

Thanks for the reply. Activities were created under WBS only. But what went wrong I don't know. I still haven't figured it out yet. As of now, it looks like that I will have to assign the WBS to all these activities one by one. 

Thanks again for the reply.

Zoltan Palffy
User offline. Last seen 16 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

Try to summarize the project again but from what I see it looks like activities have not been assigned to a wbs

go to tools then summarize