Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Activity Spreadsheet Usage / P6 V8.2

2 replies [Last post]
Carlos Malaspina
User offline. Last seen 9 years 28 weeks ago. Offline
Joined: 23 Mar 2016
Posts: 2
Groups: None

Hi everyone,

Right now I’m doing a contract migration from Lump-sum to Time & Material, I updated my schedule once a week but now my client need the number of hours expended by day.  

Throw the Activity Spreadsheet Usage I can found all the information but when I update an activity by hours Primavera P6 share out the hours number along all task duration.

I’m wondering if Primavera P6 V8.2 can keep the hours number entry an specific day even if the task continue for two or more days

Example:         Activity A (5 days)

 

Spent hours

Primavera P6 V8.2

I want

Monday

5h

4.2h

5h

Tuesday

3h

4.2h

3h

Wednesday

4h

4.2h

4h

Thursday

2h

4.2h

2h

Friday

7h

4.2h

7h

Thanks for your help.

Replies

Raymund de Laza
User offline. Last seen 45 weeks 1 day ago. Offline
Joined: 23 Nov 2009
Posts: 762

Use bucket planning

Zoltan Palffy
User offline. Last seen 15 weeks 16 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

by default Primavera spreads your manhours linerarly over the activity. To do what you want first make a cumstom curve then assign the custom curve to the resourses where you want this to happen.

go to enterprise then resource curves

then select ADD

Then name it what you want

Then Select Modify 

now for the curve values enter these values these values go across the bottom on the curve

0.0 0%

6.0 5%

6.0 10%

6.0 15%

6.0 20% 

3.5 25%

3.5 30%

3.5 35%

3.5 40%

4.8 45%

4.8 50% 

4.8 55% 

4.8 60% 

2.5 65%

2.5 70%

2.5 75%

2.5 80% 

8.2 85%

8.2 90%

8.2 95% 

8.2 100%

now assign the curve to the resource