Hi everyone,
Right now I’m doing a contract migration from Lump-sum to Time & Material, I updated my schedule once a week but now my client need the number of hours expended by day.
Throw the Activity Spreadsheet Usage I can found all the information but when I update an activity by hours Primavera P6 share out the hours number along all task duration.
I’m wondering if Primavera P6 V8.2 can keep the hours number entry an specific day even if the task continue for two or more days
Example: Activity A (5 days)
| Spent hours | Primavera P6 V8.2 | I want |
Monday | 5h | 4.2h | 5h |
Tuesday | 3h | 4.2h | 3h |
Wednesday | 4h | 4.2h | 4h |
Thursday | 2h | 4.2h | 2h |
Friday | 7h | 4.2h | 7h |
Thanks for your help.