predecessor or successor

3 replies [Last post]
vigeeth salian
User offline. Last seen 2 years 33 weeks ago. Offline
Joined: 25 Feb 2016
Posts: 10
Groups: None

hi,

 

is it important to have predecessor or successor in all the activities.

In my planning file, some doesnt have Predecessor.

will it creat any problem to my plan in later stages?

 

Plz help me

Replies

Zoltan Palffy
User offline. Last seen 1 day 11 hours ago. Offline
Joined: 13 Jul 2009
Posts: 2721
Groups: None

ALL activities MUST have a predecessor except for the very first one and ALL activities must have a successor except the last one. This is the whole concept of the critical path method.

Every activity in your schedule would have a predecessor even if its only the 1st one such as start project. If you think about it how can that activity that you claim to not have a predecessor start if you have not started the project ?

Zoltan Palffy
User offline. Last seen 1 day 11 hours ago. Offline
Joined: 13 Jul 2009
Posts: 2721
Groups: None

ALL activities MUST have a predecessor except for the very first one and ALL activities must have a successor except the last one. This is the whole concept of the critical path method.

Every activity in your schedule would have a predecessor even if its only the 1st one such as start project. If you think about it how can that activity that you claim to not have a predecessor start if you have not started the project ?

Rafael Davila
User offline. Last seen 2 hours 6 min ago. Offline
Joined: 1 Mar 2004
Posts: 4876