Predecessor and Successor

4 replies [Last post]
yifei 87
User offline. Last seen 12 years 8 weeks ago. Offline
Joined: 27 Feb 2013
Posts: 10
Groups: None

Dear Sirs,

For P6, say Task A is the predecessor as Task B and Task C is the successor for Task B.

If I delete Task B, can the linking from Task A-Task B become Task A to Task C?

Thank you

Replies

yifei 87
User offline. Last seen 12 years 8 weeks ago. Offline
Joined: 27 Feb 2013
Posts: 10
Groups: None

Thank you very much.  I think this had solve my problems.

Have a nice day.

Mike Testro
User offline. Last seen 38 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Gary

Alternatively you could change task B into a milestone to leave a record of the change.

Best regards

Mike Testro

Gary Whitehead
User offline. Last seen 6 years 12 weeks ago. Offline

Yifei,

 

If you delete Task B, you will have to manually add the link from Task A to Task C

If you instead dissolve Task B, Primavera will automatically add the new link for you

Mike Testro
User offline. Last seen 38 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Yifei

Yes

Best regards

Mike T.