Activity % Complete

3 replies [Last post]
Diane Jones
User offline. Last seen 8 years 15 weeks ago. Offline
Joined: 15 Dec 2015
Posts: 6
Groups: None

Hi,

Can anyone advise why I can't change the 'Activity % Complete'??? I have % Complete Type as 'Physical' and need to update a programme.

I'm new to this and I'm sure it's something simple, help most appreciated.

Thanks,

Diane

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

in the % compleyte type you have 3 options physical, units and duration this can be at the individual activity level and can also be set at the project level. 

the actvitiy % complete should be equal to whatever the physical, units or duraiton % complete is if not run a global change where activity % complete eqauls physical % complete. 

Zoltan Palffy
User offline. Last seen 4 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

in the % compleyte type you have 3 options physical, units and duration this can be at the individual activity level and can also be set at the project level. 

the actvitiy % complete should be equal to whatever the physical, units or duraiton % complete is if not run a global change where activity % complete eqauls physical % complete. 

leighton rogers
User offline. Last seen 8 years 12 weeks ago. Offline
Joined: 9 Jan 2016
Posts: 15
Groups: None

Hi Diane

 

Im realitivity new to this as well

Have you started the activity? and checked the activity box to started in the status bar? then update the physical % complete

 

regards

 

leighton