Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Float bars on finished tasks

No replies
Alexandre Faulx-B...
User offline. Last seen 1 year 51 weeks ago. Offline
Joined: 20 Jan 2003
Posts: 1355

Hello planners,

can somebody please explain why Primavera P6 V7 or R8 displays a float bar when a task is completed, eventhough the Free float and Total float fields are empty?

these tasks are not out-of sequence

the float bar goes until the remaining start of the first successor in sequence

this happens for tasks wiche were critical or not critical all the same; how can it be possible to draw a float bar for a completed task?

thank you for your help and explanations

Alexandre