Hello planners,
can somebody please explain why Primavera P6 V7 or R8 displays a float bar when a task is completed, eventhough the Free float and Total float fields are empty?
these tasks are not out-of sequence
the float bar goes until the remaining start of the first successor in sequence
this happens for tasks wiche were critical or not critical all the same; how can it be possible to draw a float bar for a completed task?
thank you for your help and explanations
Alexandre