Global Change to remove all logic/relationships to external projects?

1 reply [Last post]
V Kutty
User offline. Last seen 5 years 28 weeks ago. Offline
Joined: 17 Jan 2011
Posts: 23
Groups: None

Hi All

 

Just wondering if theres a way of removing all activity relationships to external projects via a global change?

 

Thanks for any pointers

 

V

Replies

Zoltan Palffy
User offline. Last seen 11 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

go to the schedule options and check ignore relationships to and from otherl projects

also if you export this file to xer then import the file back in durign the importing porcess select modify and under the Data Type: Project section in the Relationships to external Projects you can choose DO NOT IMPORT