Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Global Change to remove all logic/relationships to external projects?

2 replies [Last post]
V Kutty
User offline. Last seen 4 years 7 weeks ago. Offline
Joined: 17 Jan 2011
Posts: 23
Groups: None

Hi All

 

Just wondering if theres a way of removing all activity relationships to external projects via a global change?

 

Thanks for any pointers

 

V

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 5 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

why not go to the scheduling option and turn OFF the link to external projects

Ahmed Aziz
User offline. Last seen 8 years 19 weeks ago. Offline
Joined: 12 Aug 2014
Posts: 25
Groups: None
Hi kutty, I am afraid you cant remove the relations by a global change instead tgere are two other ways: 1. Copy and paste the project and unmark "copy aexternal activity relations" 2. Export to excel (only relationships) open the excel sheet "taskpred". Filter the activities from other project, put a " d" in tge column named "delete this row", import to primavera. Aziz