Critical Activities not showing

9 replies [Last post]
Binita Shakya
User offline. Last seen 10 years 48 weeks ago. Offline
Joined: 25 Jun 2014
Posts: 3
Groups: None

I am new in Primavera P6. I built a schedule in Primavera, with activities from 18-Sep-2012 to 02-July-2014. I have its data date of 18-Sep-2012. But this schedule doesn't show critical activities as it should. It have large number of total floats, whereas those floats should be zero. Would somebody please help me to solve this problem.

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

if you remove the Project Must finish by date you will NEVER see any negative float if the project falls behind schedule.

make sure each activity has a predecessor and each activity has a successor the float is what it is.

Yanqing Gong
User offline. Last seen 9 years 5 weeks ago. Offline
Joined: 20 Mar 2012
Posts: 10

Just remove the "Must Finish Date", and then schedule your plan, there must be some critical activities showing.

Yanqing Gong
User offline. Last seen 9 years 5 weeks ago. Offline
Joined: 20 Mar 2012
Posts: 10

I think you should first know the detail definition of Total Float, TF=LF-EF, in other words, TF is the most buffer duration that a activity can float from early start of finish date to late start or finish date, but not affecting the delivery date. So if a acitivity has a huge TF, you should first consider that if it has a successor activity.

Zoltan Palffy
User offline. Last seen 3 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

1. go to the Projects directory check the project must finish by date make sure that the DATE is correct

2. make sure that every activity has a predecessor except the first activity.

3. Make sure that every activity has a successor expect the last activity in the schedule.

 

 

Ahmed Aziz
User offline. Last seen 9 years 32 weeks ago. Offline
Joined: 12 Aug 2014
Posts: 25
Groups: None

Hi Binita,

Could you please send a screenshot showing the start, finish and total floar columns and the gant chart. without seeing the schedule I won't be able to help you.

Ravi Katare
User offline. Last seen 10 years 51 weeks ago. Offline
Joined: 14 Jul 2014
Posts: 23
Groups: None

Hi Binita,

At project level (Date Tab), have you applied any must finish date gerater than 02-July-2014? If yes, remove it

- Ravi 

Jerome Odeh
User offline. Last seen 6 days 7 hours ago. Offline
Joined: 19 Jan 2004
Posts: 107

Binita,

Check to make sure you don't have dangling activities (SS relationships).

You need proper logic (mainly FS relationships) for you to have meaningful Total Float.

 

=jerome

Binita Shakya
User offline. Last seen 10 years 48 weeks ago. Offline
Joined: 25 Jun 2014
Posts: 3
Groups: None

Thank-you for your time Jerome.

I defined relationship, but still it shows huge total float in all the activities.

Jerome Odeh
User offline. Last seen 6 days 7 hours ago. Offline
Joined: 19 Jan 2004
Posts: 107

Binita,

Assign relationships to activities, i.e. predecessors and successors. Total Float is driven by schedule logic.

 

Jerome