User defined field / activity code with several data for one activity

1 reply [Last post]
nj iop
User offline. Last seen 11 years 26 weeks ago. Offline
Joined: 2 Apr 2014
Posts: 2
Groups: None

Hi,

I would like to know if it is possible to create an activity code or user defined field with several data for one activity (like for the predecessors where the activity can have sereval of them).

Best Regards,

Replies

Rangarajan Ramaswamy
User offline. Last seen 3 years 1 week ago. Offline
Joined: 1 Dec 2009
Posts: 24

Yes its possible. Add all the activity codes that you want to one activity and then enable the activity codes column and then just use fill down to copy the activity codes to all the required activities.