S curve based on Financial Period Data

1 reply [Last post]
mani M.R
User offline. Last seen 10 years 8 weeks ago. Offline
Joined: 4 Aug 2009
Posts: 21

Hai all

I heared that there will be minor difference in S curve when we compare between Actual & Earned value based on Store Period perforrmance Data & without store Period Performmance Data.

 

Can anyone say me how it will differ ?

 

Which is the best method to compare (Based on Store Period  Performmance or without store period performmance data)

 

Regards

Mani

 

 

 

Replies

Ben Fleury
User offline. Last seen 8 years 37 weeks ago. Offline
Joined: 19 May 2014
Posts: 5
Groups: None

I realize you've posted this question back in 2013, but I'm seeing a situation which seems to, at least partially, answer your question.

The image I've attached is the Resource Assignments tab in Primavera. The Left side is displaying actual costs I've stored using the "Store Period Performance..." option (Columns found under "Financial Period Values"). The Right side is just my "Resource Usage Spreadsheet".

When you start to review the data, you can see that the information I've stored is different than the information in the spreadsheet. (BTW, The information on the Left is the correct data). What I believe is happening is the "Resource Usage Spreadsheet" on the right is spreading the total actual cost across the duration of the activity based on the calendar set for each resource. As you can deduce, there is a slight difference between what I have stored and what is just being spread by the program. 

If anyone can explain this better, please reply. 

4348
resourceassignments_img1.jpg

 

***Tags I was searching for***
Why are my stored actual costs different?
Financial Period values are different on my Resource Assignments tab
***                                 ***