Periodic Incremental data

1 reply [Last post]
Bijaya Bajracharya
User offline. Last seen 8 years 1 week ago. Offline
Joined: 25 Feb 2005
Posts: 175
Groups: None
I save a version of programme after every monthly update. To get the incremental data for the current month, I use last month’s update as baseline. I can then use the user defined numbers to calculate the incremental value. Eg, Incremental (this month’s) earned value cost = Current earned value cost - BL earned value cost.

It is simple logic but P3ec does not seem to provide all BL variables for such operations in global change. Some more BL data are available for display in column but still not all of them.

Does anybody has idea how to get all the data items of the BL for comparison to the current (without using excel)?

Replies

David Kelly
User offline. Last seen 1 year 38 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
I am sure I answered this question in another forum?! Ho Hum.

There are a variety of ways you can address this problem (and Problem with a capital "P" it is- the lack of access to baseline fields, especially earned value, is a serious one) but first you must investigate Version 5’s Earned Value History or Past Period Actuals as some refer to it. There is a good possibility that this will solve all of your issues.