Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Level of Effort Activities

1 reply [Last post]
Kylee Foster
User offline. Last seen 9 years 12 weeks ago. Offline
Joined: 14 Aug 2007
Posts: 10

Hi All,

It seems if I assign roles to a level of effort activity before I schedule it so the activity is of the correct duration, the distribution of the role will remain on the initial duration of the activity even after I schedule.

Can anyone verify this for me?  Are there other tricks with this? 

Thanks and Regards, Kylee.

Replies

Raymund de Laza
User offline. Last seen 30 weeks 6 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Kylee,

Suggests to do the following:

1. In User Preferences ... Resource Analysis .. Review the "Interval for Time distributed resource calculations" if its matching your Time Scale.

2. After scheduling, Remove the Roles asssigned and re-assign.

 

Regards,