Level of Effort Activities

1 reply [Last post]
Kylee Foster
User offline. Last seen 10 years 20 weeks ago. Offline
Joined: 14 Aug 2007
Posts: 10

Hi All,

It seems if I assign roles to a level of effort activity before I schedule it so the activity is of the correct duration, the distribution of the role will remain on the initial duration of the activity even after I schedule.

Can anyone verify this for me?  Are there other tricks with this? 

Thanks and Regards, Kylee.

Replies

Raymund de Laza
User offline. Last seen 28 weeks 4 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Kylee,

Suggests to do the following:

1. In User Preferences ... Resource Analysis .. Review the "Interval for Time distributed resource calculations" if its matching your Time Scale.

2. After scheduling, Remove the Roles asssigned and re-assign.

 

Regards,