Absence of proper Longest Path in a Schedule with many milestones

2 replies [Last post]
Gulshan Kriplani
User offline. Last seen 10 years 45 weeks ago. Offline
Joined: 24 Mar 2009
Posts: 8
Groups: None

We are making a schedule for a building with many contractual milestones which are given constraint "finish on" in P6. These milestones are linked with each other with FS relationship and lag 0. However, with this arrangement the schedule is not showing a proper longest path. Is there any remedy for the same.

Replies

Ronald Winter
User offline. Last seen 3 years 7 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None

Gulshan,

I presented a paper on this topic at the 2005 AACE conference titled, “Managing Multiple Milestones.”  You can find a copy of it at http://www.ronwinterconsulting.com/published.htm.  Good luck!

SANTOSH KUMAR PRASAD
User offline. Last seen 7 years 13 weeks ago. Offline
Joined: 16 Aug 2010
Posts: 13
Hello Gulshan Firstly check schedule Open ends, if there work on it with proper logic. After that link your milestone A) start Milestone : link with group latest start successor activity with SS 0 lag relationship. B) Finish Milestone : link with group last finish successor activity with FF 0 lag relationship.