Resource Allocation issue

No replies
Kevin John McGovern
User offline. Last seen 44 weeks 2 days ago. Offline
Joined: 18 Jul 2007
Posts: 4
Groups: None

Hi, I am using V23.12.

I have a fairly small schedule which is fully resource loaded. All dates etc. are correct folowing update.

However, on one activiy in particular, the resource loading has been spread way beond the activity completion date.

Activity completion date is 23 Sept and the resource loading goes on into November. Curve is linear and late dates are only 2 days beyond finish dates.

Anybody any ideas how to correct this?

Thanks

Zoltan Palffy
User offline. Last seen 2 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3090
Groups: None

it should go until September becasuse 23 Sept is you completion date

are you looking at remaing early histogram ?

Hamza BENOUFIR
User offline. Last seen 1 week 2 days ago. Offline
Joined: 22 Jan 2020
Posts: 18
Groups: None

If it's okay for you, can you share with us the cause of the issue?

Hamza BENOUFIR
User offline. Last seen 1 week 2 days ago. Offline
Joined: 22 Jan 2020
Posts: 18
Groups: None

If it's okay for you, can you share with us the cause of the issue?

Kevin John McGovern
User offline. Last seen 44 weeks 2 days ago. Offline
Joined: 18 Jul 2007
Posts: 4
Groups: None

Apologies for all the duplicate messages. No idea how that happened.

Anyway, issu is now solved :)

Kevin John McGovern
User offline. Last seen 44 weeks 2 days ago. Offline
Joined: 18 Jul 2007
Posts: 4
Groups: None

Apologies for all the duplicate messages. No idea how that happened.

Anyway, issu is now solved :)

Kevin John McGovern
User offline. Last seen 44 weeks 2 days ago. Offline
Joined: 18 Jul 2007
Posts: 4
Groups: None

Apologies for all the duplicate messages. No idea how that happened.

Anyway, issu is now solved :)

Alex Lyaschenko
User offline. Last seen 3 weeks 1 day ago. Offline
Joined: 15 Aug 2011
Posts: 59
Groups: None

If it is ok for you. I can run your schedule via external schedule analysis tool to identify the problem. 
 

Alex Lyaschenko

Kevin John McGovern
User offline. Last seen 44 weeks 2 days ago. Offline
Joined: 18 Jul 2007
Posts: 4
Groups: None

Further udate on the above.

My data date is 04 Aug and I have activities already completed in July. However, the resource Assignments spreadsheet shows the planned resource going on until September.

This has me completely stumped 

Kevin John McGovern
User offline. Last seen 44 weeks 2 days ago. Offline
Joined: 18 Jul 2007
Posts: 4
Groups: None

Further udate on the above.

My data date is 04 Aug and I have activities already completed in July. However, the resource Assignments spreadsheet shows the planned resource going on until September.

This has me completely stumped 

Kevin John McGovern
User offline. Last seen 44 weeks 2 days ago. Offline
Joined: 18 Jul 2007
Posts: 4
Groups: None

Further udate on the above.

My data date is 04 Aug and I have activities already completed in July. However, the resource Assignments spreadsheet shows the planned resource going on until September.

This has me completely stumped 

Kevin John McGovern
User offline. Last seen 44 weeks 2 days ago. Offline
Joined: 18 Jul 2007
Posts: 4
Groups: None

Further udate on the above.

My data date is 04 Aug and I have activities already completed in July. However, the resource Assignments spreadsheet shows the resource goin on until September.

This has me completely stumped 

Kevin John McGovern
User offline. Last seen 44 weeks 2 days ago. Offline
Joined: 18 Jul 2007
Posts: 4
Groups: None

Further udate on the above.

My data date is 04 Aug and I have activities already completed in July. However, the resource Assignments spreadsheet shows the resource goin on until September.

This has me completely stumped