Task mode in activity Zero

1 reply [Last post]
Alex Lyaschenko
User offline. Last seen 52 min 9 sec ago. Offline
Joined: 15 Aug 2011
Posts: 41
Groups: None

Hi Helpers,

Is it a way to change TASK MODE for activity ZERO (Project summary)?

 

Regards,

Alex Lyaschenko 

Replies

Rodel Marasigan
User offline. Last seen 18 min 53 sec ago. Offline
Joined: 25 Oct 2006
Posts: 1696

It is not possible. It always default to Auto and cannot be manuall. It always calculate overall project duration even with no task.