Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Activity cannot finish until another - zero float

3 replies [Last post]
smithie johnny
User offline. Last seen 15 years 38 weeks ago. Offline
Joined: 1 May 2008
Posts: 11
I am trying to work out how to drive logic within schedule to be finish dependent. That is the activity must finish when another activity is 50% finished, but that is has zero float between the activity finishign and the other one being 50% completed?

Like the idea of JIT -- "just in time": so the car seat gets manufacturered in a timeframe driven by when it needs to be assembled into the car, so that ther is zero float between the seat arrives onsite at the car factory, and the seat needs to be installed into the car.

How do i set up P3 to deliver this outcome???

Replies

Frank Borcherdt
User offline. Last seen 7 years 17 weeks ago. Offline
Joined: 3 May 2001
Posts: 88
Groups: None
Two ways to try:-

1. Activity A 20days FF to Activity B 2 days then reschedule changing Schedule Durations option from Contigous to Interruptible and back (found in Tools, Schedule, Options). No percentage option in P3 but you could put -10 days lag on the FF.

2. Activity C 10 days FS to Activity D 10 days and Activity E 2 days with FS between E and D. Put Zero free float constraint on E.

No a big fan of FF so I tend to use method 2 and define what needs to happen before E is required and then what can happen once it has arrived.

HTH
smithie johnny
User offline. Last seen 15 years 38 weeks ago. Offline
Joined: 1 May 2008
Posts: 11
Vladimir

Can you please elobrate on " no earlier than"?

Also the schedule i’m putting together doesn’t have resource contraints just time contraints. Does this help?

Is there a way to get P3 to behave to get JIT?
It is not supported if resources are limited.
All dependencies used in Primavera software are of "no earlier than" type.

The dependencies you need (JIT) are called "strong dependencies" in Spider Project software.