Different calender to summary task & Activitis

2 replies [Last post]
mukunda y
User offline. Last seen 10 years 33 weeks ago. Offline
Joined: 12 Nov 2008
Posts: 97
Groups: None

I want to assign 6 days calender to the activities & want to calculate the summary task duration based on the 7 days calender,,, is there any way to do this,,,

 

Thanks & Regards

Mukunda

Replies

mukunda y
User offline. Last seen 10 years 33 weeks ago. Offline
Joined: 12 Nov 2008
Posts: 97
Groups: None

I got it, Thank you Mike,

Mike Testro
User offline. Last seen 6 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Mukunda

I don't see why not - just create the two calendars and assign them accoringly.

If MSP won't allow that simple operation then use real software like PowerProject.

Best regards

Mike Testro