Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

MS Project 2016 - Renumber wbs of selected task is greyed out in MS project

1 reply [Last post]
Pranab Kumar Deb
User offline. Last seen 2 years 46 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291

Hi All, 

 

I am using MS Project 2016 and want to renumber a selection of activities but the renumber wbs selected task in ms project 2016 is greyed out.  I have tried the task sheet view and removing the autofilter, nothing works

 

Please help. 

 

regards

 

Pranab 

Replies