Joined: 7 Feb 2013
Posts: 52
Groups: None

I just started a new project and i entered two activities so far.

I want to select task type.

i am at task information > advanced tab, and i see the options there but they are disabled.

I can not select task type . Effort driven checkbox is also disabled

Replies

David Manna
User offline. Last seen 6 years 13 weeks ago. Offline
Joined: 26 Nov 2017
Posts: 13
Groups: None

I am learning MS project and very excited to use it for our new project. I was having the same issue. Thanks for the solution guys.  

Ahmet Tuter
User offline. Last seen 2 years 48 weeks ago. Offline
Joined: 7 Feb 2013
Posts: 52
Groups: None

thanks you are right. they were manually scheduled and i turned it off

Tom Boyle
User offline. Last seen 3 weeks 5 days ago. Offline
Joined: 28 Nov 2006
Posts: 304
Groups: None

These options are disabled for summary tasks and for manually scheduled tasks.  I would suspect yours is manually scheduled.