Project with several phases of completion dates

No replies
Lo Gary
User is online Online
Joined: 7 Feb 2010
Posts: 45
Groups: None

Dear,

 

I have a project with 6 phases each has different contractual completion dates and liquidated damages. But all phases are inter-related. I consider they should have their own critical path.

It means the programme should have 6 critical paths. 

What should I do?

I use subprojects to link them together in a separate project then it will show 6 critical paths?

 

 

Regards,

 

Gary Lo