Dear,
I have a project with 6 phases each has different contractual completion dates and liquidated damages. But all phases are inter-related. I consider they should have their own critical path.
It means the programme should have 6 critical paths.
What should I do?
I use subprojects to link them together in a separate project then it will show 6 critical paths?
Regards,
Gary Lo