Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Open end tasks

4 replies [Last post]
moutaz aldeib
User offline. Last seen 2 years 26 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None

Hi All,

How we can extract report in MS project showing the open end tasks? rather than adding predessor and successor columns.

Regards,

Muataz

Replies

Tom Boyle
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 28 Nov 2006
Posts: 304
Groups: None

[Deleted]

moutaz aldeib
User offline. Last seen 2 years 26 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None

Thanks a lot Tom, however I would like to comment that in P6, once you schedule you get a report including the open end tasks.

Best,

Muataz

Mike Testro
User offline. Last seen 4 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Alternatively just look for large amounts of float.

Tom Boyle
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 28 Nov 2006
Posts: 304
Groups: None

Make a new filter called "Open Ends" with the following criteria:

- Predecessors - equals - [empty field]

Or - Successors - equals - [empty field]

For "[empty field]," enter no characters at all.

Then include this filter in your report specification - or just apply the filter in a view.

 

Note: this is the simplest "open-ends" criteria, same as P6, and does not include dangling starts/finishes.  Filtering danglers requires a little macro code ("vba").