Gantt Chart bars on wrong dates

2 replies [Last post]
Craig Stevens
User offline. Last seen 10 years 20 weeks ago. Offline
Joined: 24 Jan 2012
Posts: 7
Groups: None

I have added some additional tasks, including completion milestones, into the programme.  The dates in the date columns are correct, but a small number of the bars on the Gantt Chart have slammed back to 1984!

The file was originally 2007, I am working in 2010.

Its only a problem of presentation, but this is to be presented to people who technical grasp of planning is quite low. 

 

Replies

Mike Testro
User offline. Last seen 5 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Craig

Do the milestones have both Predecessor and Successor Logic?

If no Predessor you can try setting the position as ALAP - if no Successor then you will have to fix it with a constraint which is bad planning practice but needed soemtimes for presentation purposes.

Best regards

Mike Testro

Craig Stevens
User offline. Last seen 10 years 20 weeks ago. Offline
Joined: 24 Jan 2012
Posts: 7
Groups: None

I should add that it is actually only for milestones that are disappearing from the Gantt Chart, not activities with durations.

Logic lines appear on the screen (going back to 1984), but when printed these links disappear completely, meaning the unitiated have to have it explained that logic does exist, it is just not showing for some unknown reason.