I have added some additional tasks, including completion milestones, into the programme. The dates in the date columns are correct, but a small number of the bars on the Gantt Chart have slammed back to 1984!
The file was originally 2007, I am working in 2010.
Its only a problem of presentation, but this is to be presented to people who technical grasp of planning is quite low.