time scale of project 2007

J
Jian Liu 👤 Member for 15 years 2 months

all,

i want to arrange a proposal schedule by project 2007.

but i could not find how to modify the time scale like p6, from 1 2 3 ....... not from the actual date.

thanks !

E
Evgeny Z. 👤 Member for 18 years 5 months

Liu,

You can do it like this:

  1. In Gantt Chart Timescale chose Day / Week/ Month from Start
  2. Create and show customer field, which will calculate the task start date and task finish date from the Project Start

    e.g.

    Task Start from Project Start (Calendar Days)(Number1)=DateDiff("d";[Project Start];[Start])+1

This is how your schedule will look like then

 photo timescaleofproject2007_zpsab7435bb.png