time scale of project 2007

1 reply [Last post]
Jian Liu
User offline. Last seen 16 weeks 3 days ago. Offline

all,

i want to arrange a proposal schedule by project 2007.

but i could not find how to modify the time scale like p6, from 1 2 3 ....... not from the actual date.

thanks !

Replies

Evgeny Z.
User offline. Last seen 35 weeks 5 days ago. Offline
Joined: 13 Jan 2008
Posts: 442
Groups: None

Liu,

You can do it like this:

  1. In Gantt Chart Timescale chose Day / Week/ Month from Start
  2. Create and show customer field, which will calculate the task start date and task finish date from the Project Start
    e.g.
    Task Start from Project Start (Calendar Days)(Number1)=DateDiff("d";[Project Start];[Start])+1

This is how your schedule will look like then

 photo timescaleofproject2007_zpsab7435bb.png