MS Project Time Scale Error

1 reply [Last post]
Nathan Siva
User offline. Last seen 3 days 12 hours ago. Offline
Joined: 28 Apr 2014
Posts: 17
Groups: None

Good day Experts,

While changing the timescale from Days to monthly or quarterly or yearly in MS project, I'm getting the error of "Invalid argument" because of that, I cant able to change the timescale in MS project and the same MPP file I can able to change timescale in my colleagues laptop and its not able to change timescale in my laptop.

Kindly suggest.

Replies

Alexandre Faulx-B...
User offline. Last seen 3 hours 57 min ago. Offline
Joined: 20 Jan 2003
Posts: 1258

Nathan,

make sure the lower level in the timescale is not larger than the upper one:

for instance upper level = week, step: 1 is not compatible with lower level = days, step: 8

if the problem is not this one, I suggest you re-install MS Project

Alexandre