Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Working Dates Back in Project 2003

7 replies [Last post]
Mark Laker
User offline. Last seen 12 years 41 weeks ago. Offline
Joined: 6 Jul 2011
Posts: 4
Groups: None

This may be a basic question, but I want to design a plan that works back from a given delivery date. I've discovered I can enter predecessors with a minus number of days, but it doesn't appear to work the dates back consistently. Ideas?

Replies

Ismet Kocaman
User offline. Last seen 8 years 27 weeks ago. Offline
Joined: 5 Mar 2010
Posts: 26

You're welcome.

--Ismet

Rafael Davila
User offline. Last seen 1 day 46 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

The procedure of assigning ALAP constraint is no good as it will make all activities critical.

In MS Project Schedule from Finish Date shall do it, just be careful with date constraints.

If your software do not provide for a backward computation that keeps finish date fixed and display float then try fixing the project finish date to your target date. Perform a schedule run and find the Early and Late dates for Start milestone. If you are performing resource leveling remember to perform the constrained schedule using the resource leveling option. Then delete finish constraint and set DD to the Early Start of the Start Milestone you just got if the target date was moved backwards or use Late Start if project target finish was moved forward.

Even when my software provides backward computation functionality out of the box I have never been in need to use this functionality on a real schedule with intermediate date constraints. It would be interesting to see how intermediate date constraints perform as this can create some issues if you do not move them back or forward as target finish date is moved back or forward. Suggest using some logic as to keep intermediate milestone dates in control.

Gary Whitehead
User offline. Last seen 4 years 46 weeks ago. Offline

Thinking about it, another and probably better option would be to display the bar & columns for your late dates rather than making everything ALAP.

 

This gives you the option of applying other constraints to activities if required, and means you don't loose the early dates which may still be handy to know.

Mark Laker
User offline. Last seen 12 years 41 weeks ago. Offline
Joined: 6 Jul 2011
Posts: 4
Groups: None

Thanks Gary, I'm going to use this method on another project I've got coming up soon - cheers.

Mark

Mark Laker
User offline. Last seen 12 years 41 weeks ago. Offline
Joined: 6 Jul 2011
Posts: 4
Groups: None

Thanks Ismet, this worked a treat. I appreciate your help.

Mark

Ismet Kocaman
User offline. Last seen 8 years 27 weeks ago. Offline
Joined: 5 Mar 2010
Posts: 26

Planning from the Finish date is the most practical way to do backward scheduling. Project will automatically set all the new tasks with default constraint As Late As Possible (ALAP). You can set backward scheduling as follows: Project menu | Project Information... command > Project Information for ... Dialog Box | Schedule from: <select Project Finish Date> | OK

Gary Whitehead
User offline. Last seen 4 years 46 weeks ago. Offline

Create your schedule as normal, constrain your given delivery date, and set all other tasks as ALAP.