Joined: 16 Jan 2004
Posts: 68
In the ’total slack’ column it shows 0 days. But some of the bars which have 0 float are blue and others are correct coloured red. I need ALL bars to be red for criticality. What is happenning?

Replies

Stuart Atkinson
User offline. Last seen 1 year 12 weeks ago. Offline
Joined: 16 Jan 2004
Posts: 68
Thanks Guys.
Rafael Davila
User offline. Last seen 1 day 2 hours ago. Offline
Joined: 1 Mar 2004
Posts: 5229
Maybe it is an issue with the Bar Styles, it occur to me the following.

1)If using MS project 2010 go to Format Tab and make sure to tick Critical Tasks box, if a prior version look for the equivalent of this.
2)If you know how to modify Bar Styles probably you will find one bar definition is on top of critical bar definition as determined by the order on the Bar Styles table, place at or near the bottom of the table your colored bar style for critical bars. Not sure but believe at the bottom will place it on top, if not try at the beginning of the table.
3)Look on help or Google for “MS Project Bar Styles” if the above do not work.
4)Last resort would be to reset to default Gantt.

Mike Testro
User offline. Last seen 6 weeks 11 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Stuart

Check the decimals in the Total Slack column - it may be 0.45.

Best regards