Roll-up Summary in "Group By Summary"

4 replies [Last post]
ronaldo celestino
User offline. Last seen 14 years 45 weeks ago. Offline
Joined: 24 Aug 2007
Posts: 19
Groups: None
Hi everybody,

I wanted to show a Roll-up Baseline Summary Bar in "Group By Summary"... I changed the fields in "from" & "to" in bar chart by "baseline start" & "baseline finish" respectively... & I put the Group By Summary in the "show..." field...., but it did not show what i wanted...

Is anybody there encountered same problem I have...

regards,
ronald

Replies

Niek Zonneveld
User offline. Last seen 2 years 2 weeks ago. Offline
Joined: 17 Mar 2005
Posts: 188
Groups: None
I’ve had this problem as well. It’s one of the many errors (in the bar styles section) of MSP.

If you replace "baseline start" by "start" it works. In my particular schedule all first activities under each WBS started as planned so I got away with this ’workaround’.

H.T.H.
ronaldo celestino
User offline. Last seen 14 years 45 weeks ago. Offline
Joined: 24 Aug 2007
Posts: 19
Groups: None
tnx pals,

i’ll do some experimenting as u adviced james....

i’ll send email for more info jaya...

again thank u for ur time & advice...

regards

J Venkatesh PMP P...
User offline. Last seen 10 years 50 weeks ago. Offline
Joined: 7 Aug 2006
Posts: 52
Groups: GPC Qatar
Ronaldo,

can you explain more...

If u want the project summary, u can get the same by Project summary task from the options menu...

otherwise, if u want to show summary for a set/group of activities, the same can be done adding additionjal information in the Text/number field...

for any details/clarifications contact me at venkat79_j@yahoo.co.in

J
James Griffiths
User offline. Last seen 15 years 15 weeks ago. Offline
Joined: 19 May 2006
Posts: 435
Groups: None
Ronaldo,

I can’t get it to do it either. It might be to do with having formatted the grouping AFTER having saved it with a baseline.

It could be worth performing a few experiments.

HTH.

James.