overtime calculations

2 replies [Last post]
vinod raturi
User offline. Last seen 6 years 5 days ago. Offline
Joined: 14 Aug 2006
Posts: 57
Hi ,

I have a resource who works for total 11 hrs i.e 8 hrs of regular work and 3 hrs of overtime work.

How to feed this information in MS project , so that we know on a particular day what is its cost to co.

Replies

Zhang Haixiang
User offline. Last seen 3 years 24 weeks ago. Offline
Joined: 14 Apr 2005
Posts: 250
Groups: None
Hi,

you can input these info. in ’Resource Usage View’
insert a column ’overtime work’

as for your example, put 11hrs in work, and 3hrs in overtime work

for your 2nd question, i’m afraid the first row can’t be deleted.
vinod raturi
User offline. Last seen 6 years 5 days ago. Offline
Joined: 14 Aug 2006
Posts: 57
hi ,

once i entered resource cost in Resource information dialog box , can someone tell me as why cant i delete that information once i have clicked OK.

OR please tell me how i can revise that information.