Task duration depends on other task

M
M Rooseboom 👤 Member for 23 years 4 months
E
Ed van der Tak 👤 Member for 24 years 3 months

Beste M, Dear M,



Altough were dutch, i will answer this in english. Best way to solve this problem is probably to set up a structure in which codes identify the related activities. In this way you can, after modifications to the schedule, run a macro to adjust related durations.



Its not a common solution but were both seeking new and creative alternatives, I guess!



Groeten,



Ed van der Tak

Aram Planning Consultants

The Netherlands

F
Forum Guest 👤 Member for 17 years 4 months

I am faily certain that the function you are looking for is not an inbuilt function of Microsoft Project 2000.



You could probably achieve something with a couple of milestones driven by successors with %lags and span them with a parent activity, but it would not be very elagant.



Regards



Paul E Harris

Eastwood Harris Pty Ltd

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts