Task duration depends on other task
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Beste M, Dear M,
Altough were dutch, i will answer this in english. Best way to solve this problem is probably to set up a structure in which codes identify the related activities. In this way you can, after modifications to the schedule, run a macro to adjust related durations.
Its not a common solution but were both seeking new and creative alternatives, I guess!
Groeten,
Ed van der Tak
Aram Planning Consultants
The Netherlands
I am faily certain that the function you are looking for is not an inbuilt function of Microsoft Project 2000.
You could probably achieve something with a couple of milestones driven by successors with %lags and span them with a parent activity, but it would not be very elagant.
Regards
Paul E Harris
Eastwood Harris Pty Ltd