I am using MS Project 2000 and am trying the following:
I have a task and I want to plan it based upon the duration of another task (testwork for example).
So task 1 takes 100 hours and task 2 takes 25% of task 1 (so 25 hours in this case)...
..I could first calculate it but when I change the first number I have to change it everywhere in the planning..
..is this possible?
Thx