Multiple contract milestones

1 reply [Last post]
Alan Taylor
User offline. Last seen 6 years 41 weeks ago. Offline
Joined: 7 Jul 2017
Posts: 2
Groups: None
The contract contains multiple unit completion penalty milestones which are waived if the final completion milestone is achieved. The project is in serious delay. The contractor has submitted an EOT claim (TIA and owner delay events only) that is focused on delay to final completion milestone and ignores all the intermediate penalty milestones. In my opinion all penalty milestones should be included in the analysis - any comments please.

Replies

Mike Testro
User offline. Last seen 5 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Alan

Yes they should.

Instruct your contractor to impact his dely events on the tasks leading to the milestones and refuse to consider anything else until it is done.

Best regards

Mike Testro