Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

EOT on contractual milestone

9 replies [Last post]
ashraf mokhtar
User offline. Last seen 11 years 44 weeks ago. Offline
Joined: 23 Dec 2009
Posts: 11
Dear all

My project have Finish Milestone with penalties on each stage of the project, and one stage is delayed and didnot meet it’s contractual milestone.
the contractor ask for EOT although this delay will not impact the finish date of the project.

what will be the situation in this case?

thanks all.

Replies

Mike Testro
User offline. Last seen 24 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Roland

See threads #2 & #5

Best regards

Mike Testro
Roland Tannous
User offline. Last seen 13 years 19 weeks ago. Offline
Joined: 15 Oct 2009
Posts: 84
Groups: None
Dear all,

Correct me If I am wrong, the person who asked the question mentioned delay to the milestone but then stated that the project completion date has not itself been delayed.
So the reasonable answer is to see if the contract clauses allow for EOT and therefore prolongation claims for delayed milestones as well.
If it doesn’t then he’s not really allowed any EOT and any insuing prolongation claims but he can still present a Disruption/labour-overrun claim as it doesn’t really depend on the criticality of the activity itself in the schedule.
Roland
Samer Zawaydeh
User offline. Last seen 6 years 11 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Santhosh,

If the Delay is from the Client side, then the Contractor has the full right to claim for EOT not the Owner.

I agree with you, the first option should be amicable settlement.

With kind regards,

Samer
Santhosh kumar Na...
User offline. Last seen 7 years 21 weeks ago. Offline
Joined: 7 Aug 2006
Posts: 66
If the delay is form client’s side , Owner has full right to ask for EOT. As you said it has got affected in one of the deleverable milestone.
Moreover, after evalutaion of submitted EOT, cost for the extended duration a perticular mile stone(since it is not affecting) can be waived off of agreed on gentleman discussion.

The case is simple according to me coz it has not effect on project completion, so just dont apply LD on this milestone if the delay is from client.
Samer Zawaydeh
User offline. Last seen 6 years 11 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Ashraf,

This is a standard claim. You need to make sure that it is submitted as per the Conditions of Contract regarding the time of submitting the notice of the claim and the required supporting documents.

Best Regards,

Samer
Mike Testro
User offline. Last seen 24 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Ashraf

Unless the contract clearly states that the Contractor is not entitled to an EoT on an idividual milestone then he should be granted a reasonable extension for the delay caused by the employer.

The fact that no other milestone or the completion date has been affected is irrelevant.

There may well be specific costs in respect of deployed staff and plant that related to the milestone - in which case they should be paid.

Best regards

Mike Testro
ashraf mokhtar
User offline. Last seen 11 years 44 weeks ago. Offline
Joined: 23 Dec 2009
Posts: 11
Dear Mike, Samer

the client caused the delay, put this delay did not effect other milestones.

i am studying this EOT the contractor ask for time and cost for the impacted Milestone put neither the other milestones nor the finish of the project have been impacted as per the submitted impacted program.

thanks

with regards
Samer Zawaydeh
User offline. Last seen 6 years 11 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear ashraf,

Who caused the delay (Contractor or Owner)? And what is the effect of this delay on the other milestones.

Do you want to prepare the EOT or to study the EOT?

With kind regards,

Samer
Mike Testro
User offline. Last seen 24 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Ashraf

In most standard conditions of contract then:

If the Contractor is entitled to an EoT for the late delivery of the milestone then he should be awarded what is reasonable and thus be releived of LAD’s.

The same goes for all the other milestones and the final completion.

Best regards

Mike Testro