Completion and Acceptance of the Work

1 reply [Last post]
Norzul Ibrahim
User offline. Last seen 16 years 27 weeks ago. Offline
Joined: 17 Dec 2005
Posts: 165
Hi,

Based on my experience in the oil refining industry, we normally have the following to differentiate the stages of completion of the project.

1) Mechanical Completion (MC)
2) Ready For Start-Up (RFSU)
3) Provisional Acceptance (PA)
4) Final Acceptance (FA)

The above will also normally tied to the payment milestones. What is your experience?

Thanks

norzul

Replies

Norzul Ibrahim
User offline. Last seen 16 years 27 weeks ago. Offline
Joined: 17 Dec 2005
Posts: 165
???any experience to share?