Hi Planners,
I have 5 activities in sequence -
1. Door Frames
2. Door Shutters
3. Iron Mongery
4. Architraves.
These activities are NOT CRITICAL in the baseline programme. They have float in all floors of the project.
All these activities are dependent on the consultants decision, i.e. if he delays giving the main contractor the details of the items for these activities, then they are going to affect the procurement, fabrication and fixing of the above items. Lets say that the consultant has delayed giving details / specifications for all the activites. For example,
1. Details for Door frames are delayed by 10 days.
2. Details for Door shutters are delayed by 8 days.
3. Details for Iron Mongery are delayed by 12 days.
4. Details for Architraves are delayed by 6 days.
As a Main Contractor, I am entitled to an EOT for this delay in details.
Please advise if the EOT claim should be
a) for individual activities;
b) for the hammock of the delay; or
c) for activity for the maximum delay (assuming that the delays over-lap).
Replies