Using Task Work Feature

4 replies [Last post]
Prince Jhegro Per...
User offline. Last seen 20 weeks 4 days ago. Offline
Joined: 20 Mar 2020
Posts: 3
Groups: None

Greetings everyone,

May i ask your expertice about AstaPP?

WH is 8:00am - 5:00pm, Building Construction, Creation of BL Sched.

I want to use the Task Work feature in AstaPP, while doing it, i noticed that it makes my activies to finish in-between the day which allows the successor to start on the same day. I want the successor to start the next day even if the predeccessor is already finished before the end of the working hours.

May I ask someones assistance on this. 

Thank you very much in advance.

 

Prince

Replies

Prince Jhegro Per...
User offline. Last seen 20 weeks 4 days ago. Offline
Joined: 20 Mar 2020
Posts: 3
Groups: None
Thank you on your immediate reply Sir Vladimir Liberzon & Sir Ben Taunt.
Ben Taunt
User offline. Last seen 21 weeks 2 days ago. Offline
Joined: 16 Jan 2012
Posts: 113
Groups: None

Hi Prince,

Go to the Properties of the Task (right click on the task), navigate to Constraints options and select "Start on new day". This will force the task to always start the next day, regardless of when in the day your predeccessor finishes.

8525
start_on_new_day.png

Thanks,

Ben @ Asta Powerproject 

Ben Taunt
User offline. Last seen 21 weeks 2 days ago. Offline
Joined: 16 Jan 2012
Posts: 113
Groups: None

Hi Prince,

Go to the Properties of the Task (right click on the task), navigate to Constraints options and select "Start on new day". This will force the task to always start the next day, regardless of when in the day your predeccessor finishes.

8525
start_on_new_day.png

Thanks,

Ben @ Asta Powerproject 

I don't know if Asta permits to assign special calendar to dependency lag.

If yes, assign to lag 24 hours per day calendar and make it 8 hours (if your work day lasts 8 hours).

With this lag the successor will always start in the next day.