Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Week numbers in the date zone

2 replies [Last post]
Alex Hough
User offline. Last seen 2 days 9 hours ago. Offline
Joined: 10 Apr 2017
Posts: 7
Groups: None

Hi all

I have a 30 week programme that has a 2 week shutdown over Christmas. The current week numbers in the date zone show it coming out as 32 weeks, is there any way to not show week numbers over the 2 week shutdown?

ie. up to week 5, then nothing for 2 weeks, then in January start from week 6?

Thanks in advance!

Alex

Replies

Alex Hough
User offline. Last seen 2 days 9 hours ago. Offline
Joined: 10 Apr 2017
Posts: 7
Groups: None

Brilliant, that worked thanks Ben!

Ben Taunt
User offline. Last seen 1 week 3 days ago. Offline
Joined: 16 Jan 2012
Posts: 93
Groups: None

Hi Alex,

In the Date Zone Properties (right-click within the Date Zone > Properties), the line currently representing your week numbering will likely state Type = "Elapsed Units", Time Unit = "Weeks".  If you change Elapsed Units to instead be "Working Units", it will reflect your folding calendar's exceptions.  You should then see the change you want in your date zone.

7064
date_zone.jpg

Best wishes,

 

Ben @ Powerproject