Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to turn off annual weekly numbers

2 replies [Last post]
Nathan Wharton
User offline. Last seen 10 years 33 weeks ago. Offline
Joined: 30 Aug 2013
Posts: 6
Groups: None

I am trying to add week numbers to the top of the programme in the date zone. I can do this this after week 52 it goes back to week 1, but I would like the week numbers to carry on as the project I am working on is over 2 years and would like the week numbers to continue.

Does anyone have any ideas how to do this, as I know it can be done, but just cant find the right option?

Thanks

Replies

Nathan Wharton
User offline. Last seen 10 years 33 weeks ago. Offline
Joined: 30 Aug 2013
Posts: 6
Groups: None

That was exactly what I was looking for. I had Fiscal Units instead of Elapsed Units selected in the first column?

Thanks for the quick reply

Robert Hughes
User offline. Last seen 7 years 37 weeks ago. Offline
Joined: 20 Oct 2006
Posts: 32
Groups: None

Nathan,

Right click on the date zone and select properties from the menu that opens up to open the 'Date Zone Properties' dialogue, you then need to look to the right-hand side of the 'General' tab. In the box you need to select

Type: Elapsed Units

Time Unit: Elapsed Weeks

Quantity: 1

By the sound of things you have selected 'Annual Units' instead of 'Elapased Units' in the first column. Hope that helps!