Hi all
I have a 30 week programme that has a 2 week shutdown over Christmas. The current week numbers in the date zone show it coming out as 32 weeks, is there any way to not show week numbers over the 2 week shutdown?
ie. up to week 5, then nothing for 2 weeks, then in January start from week 6?
Thanks in advance!
Alex