Formula in Asta - Slip

1 reply [Last post]
Paul Woodley
User offline. Last seen 1 year 24 weeks ago. Offline
Joined: 2 Nov 2016
Posts: 9
Groups: None

Column to show "0"

-If the task is in the past AND 100% complete
-If the task is in the future and 0% complete

Columns to show result from the following formula;
(DateDiff(Start, Today)-[~LP].ActualDuration)
IF
It is in progress and being progressed.


If the task is in the past with 0% progress it should be showing a value. The difference between today and the start of the task (latest progress)

 


I hope that gives an indication and enough detail as to the requirements.

I am in a bit of a pickle. Hoping someone could shove me in the right direction. I need the following (regarding slip) Column value to show "0" IF; - The task is in the past AND 100% complete- The task is in the future and 0% complete Column value  to show result from the following formula (the bit I could get to work);DateDiff(Start,Today)-[~LP].ActualDurationIF- The task is in progress  IF the task is in the past with 0% progress it should be showing a value - the difference between today and the start of the task (latest progress)   I hope that gives the detail explicitly enough and hope someone can help out! I am tearing my hair out over this....

Replies

Mike Testro
User offline. Last seen 35 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Paul

Why go to such bother.

Set your reschedule window to block out completed tasks.

Or show the Percent complete Nr 0% to 100% and that will show the data you want. 

Best regards

Mike Testro.