Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Asta - Layout and data input query

16 replies [Last post]
David Ward
User offline. Last seen 9 years 13 weeks ago. Offline
Joined: 1 May 2016
Posts: 2
Groups: None

Just downloaded the trial version of Asta to see what all the fuss is about. I am finding it really frustrating. Can anyone help?

  1. Every time I create a new project it always starts with an 18 week lead in. Why? I don't want an 18 week lead in. I just want the start date to be on the far left of the screen rather than in the middle!
  2. There are lots of tutorials available but none specific to scheduling quantities. For example, let's say that I have a wall to build and that wall is 100m long x 3m high. I want to be able to put these dimensions (either the linear or the m2) into Asta, tell it how long it will take to build or allow it to calculate it for me (but I don't how you would do the latter) and then as the work proceeds starting drawing down the quantities, so that in Week 1, if I input 10m (or 30m2) have been constructed I want Asta to work out the percentages for me and update itself accordingly.
  3. How do you populate the columns other than start, finish and duration with are obvious. The Add Column function lists lots of columns but I have no idea where the data comes from to populate. For example, I can insert a 'Quantity Column' by Add Column>Resource>Quantity but cannot input any data into it. The data must come from elsewhere. I have no idea where or what I must do to get the column to display the information I need.

Thanks in advance for any advice offered.

Replies

Ben Taunt
User offline. Last seen 1 year 34 weeks ago. Offline
Joined: 16 Jan 2012
Posts: 113
Groups: None

Hi David,

Have your queries been answered now or is there anything further we can help you with?  Please do give our office a call if you would like to talk through any specific frustrations you are still having with orientating yourself around the product.

Thanks,

Ben @ Asta Powerproject

Hi Mike

Thank you for your short answer to my long questions.

Best Regards,

Vladimir

Mike Testro
User offline. Last seen 35 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Vladimir

Yes. Any down time for either excavator would be set on the calander for the allocated task - not the resource.

Best regards

Mike T.

Mike, I believe that resources may have different calendars.

I remind you that you answered: "Are you saying that your excavators have a different work pattern? One Catholic and the other Jewish?" to my question about determination of activity duration when assigned resources have different calendars and productivity. You did not answer and I expect that "pure arithmetic" does not work in this case.

I am waiting for an answer to another question: What Asta does if calculated activity duration was 5 days, one of the excavators already worked for 5 days and the second excavator is still busy on another job?

Do you know the answer?

Mike Testro
User offline. Last seen 35 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Vladimir

You can apply different work patterns and calendars to different resources. They can be changed at any time.

Resource calendars over rule task calendars so you have toremeber what you have done or it gets confusing.

Best regards

Mike T.

Mike, there are many reasons for potential different work patterns of people and machines.

Among them are different times and duration of scheduled repairs, the need of partial use of certain resources on the parallel jobs, etc.

Do you need other examples when assigned resources have different work calendars?

If I understood you properly in Asta productivity (rate) is activity property and is set manually. If resource crew was changed the user shall use some other tool for determining new activity rate and enter it manually. It does not change automatically when resource crew is changed.

Am I right?

And remembering that Asta does not model team work each excavator may work at different time just because it became available earlier or later than another one. If one started to work earlier than another what will happen with assignment durations?

What Asta does if calculated activity duration was 5 days, one of the excavators already worked for 5 days and the second excavator is still busy on another job?

Mike Testro
User offline. Last seen 35 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420





Hi Vladimir

Are you saying that your excavators have a different work pattern?

One Catholic and the other Jewish?

 

 

 

  

 

 

Mike,

simple arithmetic does not take into account resource calendars.

Rafael Davila
User offline. Last seen 4 days 20 hours ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Mike,

You can try yourself a simple scenario, so simple it consist of a single activity.

Activity 1 500 cm rock excavation
Resource 1 [Excavator 1] production 10 cm/hr and works Monday, Tuesday and Wednesday 10 hrs/day
Resource 2 [Excavator 2] production 15 cm/hour and works on Wednesday, Thursday and Friday 10 hrs/day

If activity starts on Monday:
Monday =>> Resource 1 will produce 100 cm
Tuesday =>> Resource 1 will produce 100 cm
Wednesday =>> Resource 1 will produce 100 cm
Wednesday =>> Resource 2 will produce 150 cm
Thursday =>> Resource 2 will produce 50 cm in about 3 hours
Activity will take 3 days 3 hours.

If activity starts on Wednesday :
Wednesday =>> Resource 1 will produce 100 cm
Wednesday =>> Resource 2 will produce 150 cm
Thursday =>> Resource 2 will produce 150 cm
Friday =>> Resource 2 will produce 100 cm in about 7 hours
Activity will take 2 days 7 hours.

Every time the activity is delayed, the distribution of work is shifted, when you have many such activities and work on different hour shifts, different days it can become quite complicated. For a single shot you can use manual distribution of work among shifts for anything else distributing work by hand is nuts.

How would you model such simple scenario in Asta, a single activity, two resources? Cannot be any easier.

Best Regards,

Rafael

Mike Testro
User offline. Last seen 35 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Vladimir

You know the total volume and you know the outputs.

Simple arithmentic tells you how to split the volume.

Best regards

Mike Testro

Mike, the volumes of each excavator are not known before scheduling.

Mike Testro
User offline. Last seen 35 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Vladimir

I would split the tasks and assign a volume to Excavators A and B - balancing the assigned volume to create the same completion date against the known output.

They would both have the same predeccesor and successor and run concurrently.

Best regards

Mike T.

Rafael Davila
User offline. Last seen 4 days 20 hours ago. Offline
Joined: 1 Mar 2004
Posts: 5241

http://www.astadev.com/wp-content/uploads/2012/06/Whats-new-in-Version-12.pdf

ASTAVW01 photo AVW01_zps8ucngr70.jpg

The above illustration is for a calculator that has nothing to do with resources.

I would like to see a print screen of the permanent resource dialog resource modeling section where you can calculate the duration of the task by any combination of work v output v gang size (allocation) = duration. Then I would like to see how it works. By the description it looks like it fixes duration of task using a rudimentary calculator and does not respond automatically to available resources.

Mike,

I hope that David understood how Asta works with activity volumes. I did not.

It looks like I shall study Asta tutorial if it is available.

Can you explain it using simple example like this:

Earthwork is done by two excavators with different capacities (trucks amount is sufficient to make them busy).

Productivities of each are known, calendars of each are known, total volume of work (m3) is known. How Asta calculates original and remaining (after entering actuals) duration?

I know that Asta has problems with team assignments, so let's suppose that excavators work independently of each other.

Thanks,

Vladimir

Mike Testro
User offline. Last seen 35 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi David

Sorry but I missed your original thread.

One reason why you are getting an "18 week lead in" could be the calendar setting is giving you a long non working period and you have pitched your start date in the middle of it.

There are a lot of standard preset calendars that you can use or there is a calendar wizard to help you get started.

Use the task properties > dates to see what calendar is attached to your task.

The columns act as a standard spreadsheet that shares data with the tasks - similar to Spider.

The permant resource dialogue has a resource modelling section where you can calculate the duration of the task by any combination of work v output v gang size (allocation) = duration.

When you have allocated your permant resource to a task then all the data can will show on the column. It can be changed in either the task or the column.

This feature is really useful when you are copying a range of data from an excell spreadsheet ( I prefer Lotus 123) into an Asta spreadsheet - such as %progress - it is done in seconds.

Keep at it - you will find the benefits are worth the effort.

Best regards

Mike Testro

David,

like you I am waiting for the answers to your questions given by Asta users.

I want to learn how packages other than Spider Project manage work quantities.

Using quantities requires to use resource productivity. Activity duration shall depend on activity volume (quantity, amount) and assigned resources.