 I know that this is very simple to solve, but I am unable to find a solution.

When I create a new project, and go to print, the print button is faded out, and I cannot print. What I can do, is copy the project to another project and print that way. I have been throught he setting, and do not know what I have done wrong. Please help.

 

Thanks

 

Ronan

M
Mike Testro 👤 Member for 20 years 5 months

Hi Ronan

Is your printer connected?

Have you set the User Level to Advanced?

Go to Help > User Level > Advanced

A whole lot of Asta wonders will now open up.

Another possibility is that you may get better results by switching from the v 12 ribbon display to the original Icon system.

If nothing works then go to Asta support and they will sort it for you.

Best regards

Mike Testro

Forum Sponsor

Top Posters

MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Hunais M J
0 posts