Printing - Page Breaks

1 reply [Last post]
Dominic Planner
User offline. Last seen 32 weeks 5 days ago. Offline
Joined: 7 Jun 2017
Posts: 21
Groups: None

How do I ensure that the page breaks I have inserted into my programme override the pages I have scaled to, when printing?

At present, the number of pages scaled to seems to be taking precendence and it's not taking into consideration when I have applied page breaks to split my programme. 

 

Thanks 

Replies

Mike Testro
User offline. Last seen 4 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4403

Hi Dominic

Go to

Print > Options > Scaling > Fit Lines per Page (bottom right corner) > Insert nr of Lines

best regards Mike Testro